Main segments of Criterium’s 25-km SE-MGH gas pipeline in Indonesia mechanically complete, plant tie-in under way
Contractor PT Olindo has finished building and connecting the main segments of the 25-km line from the Southeast Mengoepeh gas field to the Teluk Rendah Gas Plant, and cleaning, purging and the final plant tie-in are now in progress ahead of commissioning.